Detour Route on Bukidnon-Davao Highway Closes January 4 for Final Construction Push

QUEZON, Bukidnon – The temporary detour road along the landslide-damaged Bukidnon-Davao (BuDa) Highway in Sitio Kipolot, Barangay Palacapao, will close starting 4 a.m. on Sunday, January 4, 2026, to allow uninterrupted final construction on the permanent four-lane bypass. The Department of Public Works and Highways (DPWH) Region 10 announced the closure on January 3, aiming for full opening in the first or second week of January (likely mid-January).

The detour—opened temporarily during peak holiday periods (Dec 23-26 and Dec 30-Jan 1)—served as a gravel alternative while crews built the P46.6-million permanent route. It handled heavy trucks and eased massive economic losses (~P187 million daily since the October 18, 2025, landslide that collapsed the main highway).

DPWH spokesperson Novie Cabrido confirmed: “We’re correcting the road surface grade now—with minor activities left, the detour will be fully ready by mid-January.” The permanent bypass will restore seamless travel between Northern Mindanao (Cagayan de Oro, Bukidnon) and Davao Region.

Motorist Advisory During Closure

With the detour closed, travelers must use longer alternate routes:

  • Light Vehicles: Cagayan de Oro → Valencia City → Kapalong → Talaingod → Tagum → Davao (adds ~60-100 km).
  • Heavy Trucks/Buses: Maramag → Carmen → Kabacan → Kidapawan → Digos → Davao.

The main highway remains impassable until full rehabilitation (target mid-2026). Drivers: Plan ahead, expect delays, and follow DPWH updates.

This final push ends months of disruption—safer, smoother travels soon!

Route Snapshot:

Route TypePath ExampleNotes
Temporary DetourSitio Kipolot (gravel, holiday-only)Closes Jan 4; final works underway
Permanent BypassNew four-lane (adjacent)Opens mid-January 2026
Alternate (Light)Via Talaingod/Tagum+60-100 km; longer travel
Alternate (Heavy)Via Kabacan/DigosRecommended for trucks